Step 6 - Testing after configuration

Follow these steps to test that the installation and first configuration of each communication hub and lock/sensor has been performed correctly and that the hardware is working:

  1. Check that the communication hub LED has a steady green light. This indicates that the installation and configuration have been performed correctly

    ../image28.png

  2. Hold a credential, that is configured in the EAC, in front of the lock to deny access . Result: Access is denied and the lock LED flashes red once.

    ../image29.png

  3. Hold a credential, that is configured in the EAC, in front of the lock to grant access to the lock. Result: Access is granted and the lock LED flashes green once.

    ../image30.png

See LED Indications for details on the different LED indications.